Zayan Tower Complex


Semouha Alexandria

Location:
Semouha Alexandria


Client:
Mr. Hamdy Zayan


Consultant:
Dr. Essam Kassem


Project Duration:
• Diaphragm wall works and barrettes: 6 months
• Running of Dewatering works: 20 months


Scope of Works:
• Diaphragm Wall Works
Construct outer diaphragm walls with thickness 800 mm and depth of walls is up to 30 meter. Total quantity of executed diaphragm wall is 12,784 square meter.

• Groundwater Control System
Bauer Egypt was responsible for the supply and installation of complete groundwater control system comprising 15 deep wells, piping works and alarm system. The controlling system is expected to run for about 20 months.